Passivhaus Affiliate

Palomar court pilots Passivhaus prefab

An 8-unit block of Passivhaus-certified apartments, the Palomar Court project in the Gascoigne neighbourhood of East London was constructed using an offsite light gauge steel frame system. The project, commissioned by Barking and Dagenham Council, aimed to be a pilot study using off-site construction on Passivhaus projects, exploring how prefab may apply to future phases. 

Palomar Court Passivhaus. Image credit: Collida/ Willmott Dixon

Palomar Court consists of two separate blocks connected by a communal core. The core is external to the thermal envelope envelope, and the two blocks, North & South, were submitted for Passivhaus certification separately. Based on energy modelling, the Passivhaus consultant estimates that residents will experience typical energy bills that are just an eighth of the national average. The homes are to be marketed at either London Affordable Rent or Affordable Rent levels.

 

The cost of people heating their homes is a serious cause for concern to so many households across the country in recent times. Delivering these low carbon, affordable, and energy efficient homes will help reduce our residents’ energy bills in a neighbourhood that fosters a sense of community and social wellbeing. Cllr Darren Rodwell, quote


Key stats

  • Construction: Light gauge steel frame

  • Number of homes: 8

  • GIFA:  816 m2 

  • Build start date: 2021 

  • Completed: 2023

  • Certified: Passivhaus, 2024

Gascoigne neighbourhood Passivhaus apartments. Image credit: Collida Willmott Dixon

 

Construction 

Light gauge steel panels & frame (LGSF) were specified. Offsite manufacture and assembly helped to increase efficiency as well as reduce waste. A foundation design was used that could be joined together on site like LEGO, using prefabricated XPS modules. The design team stipulated the necessity for a fully non-combustible through-wall construction, which helped the project meet Passivhaus and fire protection requirements. 

Adapting the Passivhaus requirements to the use of LGSF involved detailing the airtightness line on the external face of the wall. This was challenging as it was penetrated by the brick slip cladding.

Palomar Court under construction. Image credit: Collida Willmott Dixon Offsite manufacturing Palomar Court Image credit: Collida Willmott Dixon
Windows at Palomar Court.  Image credit: Collida Willmott Dixon Palomar Court under construction.  Image credit: Collida Willmott Dixon

 

Careful assessment of the spacing and gauge of the LGSF studs minimised the thermal bridging & ensured the robustness of this detail in PHPP (Passivhaus Planning Package). 

Building on our previous work, we completed the thermal bridging and condensation risk calculations for Passivhaus certification. The next project is likely to need fewer calculations as we build a pattern-book of typical details. Nick Devlin Quote.

 

Embodied carbon 

The specification of LGSF provided significant embodied carbon reduction. Further embodied carbon was removed from the project by eliminating avoidable waste and reusing demolition waste. The project is estimated to have around 50% lower embodied carbon emissions over its lifetime and achieved beyond LETI  benchmarks for embodied carbon. 

U-values 

Floor: 0.106 W/m2K                             

300mm concrete over 300mm XPS insulation 

Wall contruction build up at Palomar Court Gascoigne Estate. Image credit: Collida/ Willmott Dixon

Wall: 0.148 W/m2K

100mm light gauge steel frame stud with 240mm mineral wool and brick slip cladding 

Roof: 0.075 W/m2K

300mm XPS insulation.

 

Palomar Court Passivhaus project. Quote:

 

Building performance 

Designed energy performance 

 

North block

South block 

Airtightness n50 (≤ 0.6ACH @ 50 Pa)                           

 

0.4 @ 50 Pa

 

0.4 @ 50 Pa

Heating Load (≤ 10 W/m²)

 

10 W/m²

 

10 W/m²

Primary Energy Demand (≤ 135 kWh/m².a)

 

124 kWh/m².a

 

120 kWh/m².a

Primary Energy Renewable Generation

 

0 kWh/m².a

 

28 kWh/m².a

Overheating %

 0

1

*+/-15 kWh/m².a allowance if offset by energy generation. See Passivhaus criteria

 

Services 

The scheme is connected to a district heat network, which meant no air source heat pumps were required,. Each apartment in Palomar Court has a dedicated MVHR (mechanical ventilation with heat recovery) system. Rooftop solar PV panels supply electricity on the south block of the apartments. 

Solar panels at F2 Palomar Court. Image credit: Collida Willmott Dixon

Challenges 

Applying Passivhaus after planning approval: The decision to aim for Passivhaus certification came after RIBA Stage 4 (Technical Design) when the client wanted to pursue a more ambitious sustainability target. The design originally featured a traditional beam and block construction with Mechanical Extract Ventilation (MEV) system. RIBA Stage 4 needed to be revisited to refine the building's design to target Passivhaus certification.

Redesign: Navigating this change of specification posed challenges, given the existing planning permissions, which constrained design modifications. The project team collaborated closely with planners to ensure that all revisions fell within the scope of non-material amendments. Through this redesign process, several significant thermal bridges were successfully eliminated, and Psi values were optimised. Additional shading was removed from the design, as overheating was no longer a problem.

Certification: Due to the substantial glazing in the core, and the evolving ventilation strategy, it was not feasible to certify the entire block as one entity as had been originally planned.Certifying the two blocks individually incurred additional air tests and reduced the overall treated area.

Steel frame: Incorporating steel frames into Passivhaus buildings involved a significant learning curve, as Passivhaus Trust guidance on the subject had not been issued when the project commenced. 

District heat network: The district heat network created some challenges for the Passivhaus Certified Designer to model,  as the consumption, energy source and distribution losses of the network needed to be captured and evidenced for certification.

Palomar Court Passivhaus. Image credit: Collida/ Willmott Dixon

 

The success of such projects necessitates the involvement and education of a collaborative supply chain partner, a Stage 5 set of detailing and sequencing to be complete prior to commencing works, and a robust quality management audit on site.  

Lorna Taverner, Head of Collida Design, Willmott Dixon 

Lessons learned 

The project acts as a useful template for how to deliver Passivhaus using a LGSF system. Passivhaus projects constructed using LGSF or steel frame systems (SFS) are likely to be adopted more widely, due to fire regulations and the increased adoption of Modern Methods of Construction (MMC). 

For similar future projects, the design team would hope to simplify the design to ensure that Passivhaus certification could be undertaken for one entity, rather than being broken down into parts. 

Key team 

  • Client: BeFirst/ Barking & Dagenham Council

  • Architect: White Arkitekter, Collida/ Willmott Dixon 

  • Passivhaus Designer: Architype             

  • Contractor: Collida/ Willmott Dixon

  • Structural engineer: Civic Engineers

  • M&E consultant: SVM Consulting Engineers

  • Passivhaus Certifier: WARM

Gascoigne neighbourhood Passivhaus apartments. Image credit: Collida Willmott Dixon



You may also like

Technical Guidance - Steel in Passivhaus ConstructionTechnical Guidance - Steel in Passivhaus Construction
Passivhaus Social Housing Campaign
How to build a Passivhaus

 

 

Further information 

Gascoigne neighbourhood Passivhaus homes

Passivhaus Social

Passivhaus Social Housing 2024 webinar series

Passivhaus Benefits Guide & costs research 

Technical Guidance: Passivhaus overlay for RIBA Plan of Works

Technical Guidance: Steel in Passivhaus Construction

Previous PHT Story: Caerphilly does it - 7 February 2023

Previous PHT Story: London housing projects loom large - 15 December 2022

Previous PHT Story: Social housing championing Passivhaus at scale - 12 May 2021



2nd April 2024


Get involved with the UK Passivhaus community

Passivhaus Trust Membership Passivhaus Learning Hub Passivhaus Trust Mailing List Passivhaus Trust Events

< Back To News